Creating a Resource Group

  1. Go to Resources > Groups. and click on the folder icon.

    Figure 39. Action Tool

    Action Tool

  2. For the Type, most often Static is used.

    Name and description. Typically, the name will correspond to either the Environment the Resource participates in, the Component that uses the Resource Group, or a combination of both (e.g., SIT, DB, or SIT-DB). What description you give depends on how you intend to use the Resource that this Group is assigned to, etc.

    Figure 40. Create a Resource Group Dialog

    Create a Resource Group Dialog

  3. Once the Resource has been created, select the pencil icon to edit the Group.

    Figure 41. Add a Resource Dialog

    Add a Resource Dialog

  4. Once you assign a Group to a Resource, you add Subresources. A subresource enables you to apply logical identifiers, or categories, within any given Group. During deployment configuration, you can Select a given Subresource that the Process will run on. To create a Subresource, select the New Resource icon for the Group. Configuration is similar to Resource Group creation.

    Figure 42. Sub-resources

    Sub-resources

loading table of contents...