Creating Approval Items

You can create Approval items that will subsequently be approved as part of the release life cycle. These help to enforce the release processes you have defined.

For details on each type of approval, see the following topics:

Creating Milestone Items

Creating Stage Gate Items

Creating Release Approval Items

Creating Milestone Items

From the Milestones tab of a release train, you can define milestone items based on activities that you want to approve at various points throughout the release. For example, when Agile stories or use cases are complete, when all features of the planned development are complete, and when certain test phases are complete, such as sanity and integration testing. Milestone dates are date based.

From the Milestones tab of a release train or application release, you can:

To create milestone items:

  1. On the Milestones tab, click Create Milestone.
  2. Enter a descriptive title or accept the automatically-generated name.
  3. Specify a due date for the milestone.
  4. Enter a description if more detail is needed.
  5. Select an owner.
  6. If you want to allow individual users with the same role as the selected user to approve if needed, select Yes for Allow Override Approvals.
  7. Click Submit.

    Release train and application release milestone items are submitted into and enforced through the Approvals process app workflow.

Note: You can create multiple milestone items for a release train.

Tabs

The tabs available from a milestone once it is created are as follows:

Creating Stage Gate Items

From the Stage Gates tab of a release train, you can define exit criteria items that must be verified and approved before the release train can leave each stage, Scoping, Construction, and QA.

From the Stage Gates tab of a release train, you can:

To create Stage Gate Exit Criteria items:

  1. On the Stage Gates tab, click Add <stage> Exit Criteria, where <stage> is Scoping, Construction, or QA.
  2. Fill out the form as follows:
    • Enter a descriptive title.
    • Select an owner.
    • Select the environment to which the exit criteria item applies. For example, DEV, INT, UAT, or PROD.
    • Enter a description if more detail is needed.
    • Select a Release Manager for this item.
    • Click Submit.

      Release train stage gate exit criteria items are submitted into and enforced through the Approvals process app workflow.

Note: You can create multiple exit criteria items for each of the stage gates.

Tabs

The tabs available from an exit criteria item once it is created are as follows:

Creating Release Approval Items

The release approvals for release train, Train, Development, and Executive Approval, may be required before the train can start the scoping stage, QA stage, and deployment or Production stage, respectively.

From the Approvals tab of a release train, you can:

To create Release Approval items:

  1. On the Approvals tab, click Create <approval type> Approval, where <approval type> is Train, Development, or Executive.
  2. In Approval Type, select the level of approval, Level 1 up to Level 4.
  3. Depending on the level you chose in Approval Type, select the approvers for each required level of approval.
  4. If you want to allow individual users with the same role as the selected user to approve if needed, select Yes for Allow Override Approvals.
  5. Click Submit.
Note: You can create only one approval item for each of the Release Approval types for each release train.

Tabs

The tabs available from an approval item once it is created are as follows:

Release train approvals items are submitted into and enforced through the Approvals process app workflow.

Related Topics

About Approvals

Customizing Approvals