Approving ChangeMan ZMF Change Packages to PROD

After the ChangeMan ZMF Execution Provider configuration has been added or updated as needed, users, such as Release Managers, can approve ChangeMan ZMF change packages to production, the final approval for distribution and installation, through deployment tasks.

Note: The ChangeMan ZMF install is dependent on the scheduler chosen for the change package. It will be time dependent or immediate, depending on the scheduler chosen.

The fields that are displayed when configuring the deployment tasks to approve change packages to production are described in the following table.

Field Description Example Values
Title A descriptive name of the deployment task Approve to Prod
Description A longer description that explains what the task does This task approves the change package so that it will be automatically distributed and installed at the time scheduled on the ChangeMan ZMF calendar
Action Select Approve (PROD).
Environments Select from environments configured in the deployment path. For example, Dev, Test, and Prod. <select Prod>
Approver For each selected environment, select the final approver. These are the final approvers set up in ChangeMan ZMF. <select final approver>

After you create the deployment task, the task appears in the list in red, and you must then associate the related change package with the deployment task. See Linking Deployment Units to Deployment Tasks.