Adding an allocation
A resource allocation is when you make a resource available for work on a work item. He or she can be allocated to a work item, a task-based work item, or an activity-based work item. For a task-based work item, the user needs to be allocated to the work item before he or she can be assigned to a task.
- Open the Resources module.
- Select the Allocations tab.
- Click New Allocation.
- In the Resource Allocation dialog box, select a resource from the Resource drop-down.
- From the Investment drop-down, select the work item to which the generic allocation will be made. In the Select Investments dialog box, choose the work item and click OK.
- From the Role on Investment drop-down, select the resource role you want to associate with the allocation.
- From the Status drop-down, indicate whether the generic allocation is Proposed or Committed.
- Click Plus to define how much and when a resource will be allocated. For each resource allocation, define the percentage of full time (% FTE), the start and finish dates for the allocation, and any comments specific to the allocation. (Click Delete to remove a resource allocation definition.)
- Click Rates to define the rates associated with the allocation.
- Click OK.
Adding a generic allocation
A generic resource allocation is when you use a placeholder to allocate a resource instead of allocating an actual resource. When a generic resource has the same name as a resource role, it can help simplify the process of identifying the actual resource who needs to be assigned. A generic resource can be allocated to a task- or an activity-based work item. For a task-based work item, the generic resource needs to be allocated before a task can be assigned.
- Open the Resources module.
- Select the Allocations tab.
- Select a resource team in the resources tree, right-click and select New Generic Allocation.
- In the Resource Allocation dialog box, select a resource role from the Resource Role drop-down.
- From the Investment drop-down, select the work item to which the generic allocation will be made. In the Select Investments dialog box, choose the work item and click Save.
- From the Status drop-down, indicate whether the generic allocation is Proposed or Committed.
- Click Plus to define how much and when a generic resource will be allocated. For each generic resource allocation, define the percentage of full time (% FTE), the start and finish dates for the allocation, and any comments specific to the allocation. (Click Delete to remove a generic resource allocation definition.)
- Click Rates to define the rates associated with the role.
- Click Save.
Adding a team allocation
A resource team allocation is when you make an entire resource team available for work on a work item. The primary resource role of each person in the team is selected by default and cannot be edited. The resource team can be allocated to a task-based work item or an activity-based work item. For a task-based work item, the resource team needs to be allocated to the work item before resources can be assigned tasks.
- Open the Resources module.
- Select the Allocations tab.
- Select a resource team in the resources tree, right-click and select New Team Allocation.
- In the New Team Allocation dialog box, select a resource role from the Resource Team drop-down.
- From the Investment drop-down, select the work item to which the generic allocation will be made. In the Select Investments dialog box, choose the work item and click OK.
- From the Status drop-down, indicate whether the generic allocation is Proposed or Committed.
- Click Plus to define how much and when a resource will be allocated. For each resource allocation, define the percentage of full time (% FTE), the start and finish dates for the allocation, and any comments specific to the allocation. (Click Delete to remove a resource allocation definition.)
- Click Rates to define the rates associated with the allocation.
- Click OK.
Deleting an allocation
If you no longer need a resource allocation, you can delete it.
- Open the Resources module.
- Select the Allocations tab.
- Select a resource team.
- Select a resource in the resource team and click the work item to which they are allocated. Click Delete to delete the resource allocation.
Substituting a resource
You can substitute a resources who have been allocated, including substituting generic resources for actual resources. For example, if you have a generic allocation for project manager at 300% (essentially three project managers), you can substitute three user resources at 100% each, six resources at 50% each, or virtually any other combination; you can also substitute one project manager at 100% and leave the other 200% allocated to the generic resource.
- Open the Resources module.
- Select a work item.
- Select the Allocations tab.
- Select a resource from the resource tree and right-click to open the Resource Substitution dialog box.
- Select the Effective Date of Substitution. This is the date upon which the resource substitution will occur.
- Select the resource you want to substitute. Click to open the Find Resource dialog box.
- From the Resource Role to Use drop-down, select the resource role you want to associate with the allocation.
- Click OK.