Projects → Task Plan → Viewing Options → Gantt Chart → Showing non-critical tasks
The critical path is based on the longest possible sequence of tasks, factoring in their start dates, finish dates, dependencies, and constraints, and then comparing the calculated finish date of the last task in the sequence to the planned finish date for the task plan. The critical path is shown in red in a task plan. You can filter out critical tasks, so that you can idenfity and focus on the non-critical tasks in your task plan.
To show non-critical tasks