Projects → Task Plan → Viewing Options → Gantt Chart → Showing a baseline
A baseline is a snapshot of task plan data that can be used to compare the original project with the current project. The initial baseline should be used to represent the original, approved scope of a task plan, including its costs, dates, durations, labor assignments, and so on. It should be set after the task plan has been created, but before any work on a task plan is started.
To show a baseline in the Gantt chart