Projects → Task Plan → Dialog Boxes → Task Information → Task Information, Advanced → Indicating whether a task is a milestone task
A milestone task is a task that has a duration of zero days. A milestone is a special task that is used to represent an event in your project. Milestone tasks are displayed as diamonds in the Gantt chart and Network diagram.
To indicate that a task is a milestone task