Indicating whether a task ignores resource calendars

A resource generally is associated with a calendar. You can configure a task in a task plan to ingore any assigned resource's calendar for the purposes of scheduling the task in the task plan.

To indicate that a task ignores resource calendars

  1. Open the Projects module.
  2. Select an item.
  3. Select the Task Plan tab.
  4. Select a task in the task plan.
  5. Open the Task Information dialog box.
  6. Select the Advanced tab.
  7. Select Ignore Resource Calendar.
  8. Click Close.