Projects → Task Plan → Dialog Boxes → Task Information → Task Information, Advanced → Editing a task's earned value method
Earned value is a way to measure the performance of a task plan by using a series of calculations to compare actual and expected costs over the life of the project. All earned value calculations are measured by comparing the dates saved as part of the original baseline in the task plan to a specific date of your choosing, up to the current date. You can use two methods to calculate earned value: percent complete (the progress made against a task, expressed as a percentage) or physical percent complete (a manually entered value that is sometimes used as an alternative to budgeted cost of work scheduled, BCWS).
To edit the earned value method used for a task