A constraint is a requirement related to a task's start or finish date. A constraint affects how an individual task's start and finish dates are affected by its relationships to other tasks in a task plan. There are two types of constraints: flexible and inflexible. A flexible constraint is one that does not require a specific start or finish date. An inflexible constraint is one that does require a specific start or finish date.