Typically, you should approve items from the release train. Some users
may only be approvers, and may only have the Approvals application in their
Release Control
Release Ctrl application group. Those users must
approve using the Approvals application.
Information on how to approve is given in the following sections:
Approving Release Approval Items
Approving Milestone and Stage Gate Items
Approving Release Approval Items
For Release Approvals, the action
Ready for Approval must be done before you see
the options to complete or reject the item. This is typically done by the
Release Manager. After the item is ready for approval, an approver for each
level of approval must approve or otherwise action the item.
Ready for Approval
To make the Release Approval item ready for approval:
- From a release train, from the
Details/Approvals tab, click
Ready for Approval in the
Actions list.
- From a release train, from the
Details/Approvals tab, open the item you want to action. Click
More to select from other options, and then
click
Ready for Approval.
- From the Approvals application, from the list of items, open the
item you want to action. Click
More to select from other options, and then
click
Ready for Approval.
Approval
To approve Release Approval items, or otherwise
take action on them, you can do one of the following:
- From a release train, from the
Details/Approvals tab, click
Approve,
Override,
Reject,
Update, or
Delete in the
Actions list.
- From a release train, from the
Details/Approvals tab, open the item you want to action and
click
Approve,
Reject, or
Update. Click
More to select from other options.
- From the Approvals application, from the list of items, open the
item you want to action and click
Approve,
Reject,
or
Update. Click
More to select from other options.
Overrides
When you choose to override an approval, the
following options are available:
-
Types of override:
- Approve for another user
- Add/Remove an approver
- Move to next level of approval
- Reject approval
- Select users to approve for
- Override Reasons
Approving Milestone and Stage Gate Items
To confirm milestones or stage gate exit criteria
are complete, or otherwise take action on them, you can do one of the
following:
- From a release train, from the appropriate tab,
Details/Approvals or
Scehdule/Gates, click
Complete,
Reject,
Update, or
Delete in the
Actions list.
- From a release train, from the appropriate tab,
Details/Approvals or
Schedule/Gates, open the item you want to action and click
Complete or
Reject. Click
More to select from other options.
- From an application version, from the
Details/Approvals tab, open the item you want to action and
click
Complete or
Reject. Click
More to select from other options.
- From the Approvals application, from the list of items, open the
item you want to action and click
Complete or
Reject. Click
More to select from other options.
Copyright © 2012–2016 Serena Software, Inc. All rights reserved.