Adding a work item
A work item, once created, can have a resource assigned or allocated to it.
- Open the Projects module.
- Select the Work Items tab.
- Click New Work Item.
- In the New Work Item dialog box, enter a name. The following fields are optional: Start (Plan), Finish (Plan), Duration (Plan), Work (Plan), Cost (Plan), Remaining Work, Percent Work Complete, and Description.
- Click OK.
Pulling in timesheet actuals
You can pull timesheet actuals into a task. This adds data from timesheet actuals to the selected task, such as actual start date and work.
- Open the Projects module.
- Select a work item.
- Select the Work Items tab.
- Select a work item.
- Click Pull Timesheet Actuals.
Viewing a work item
Work items can be viewed from in the Work Items tab. Select a work item to view its details, assignments, and allocations.
- Open the Projects module.
- Select a work item.
- Select the Work Items tab.
- From the list of work items, select a work item. The details for that work item will be available in the lower pane.