Projects → Task Plan → Using Task Plan Tables → Default
The Default task plan table is used to view the default set of data for a task plan: name, start and finish dates, durations, and the resources who have been assigned (or allocated) to work on the task.
Default Fields | Description |
---|---|
Duration | A duration is the total amount of time required to complete a task, based on a task's start and finish dates. A duration is always based on how a day is defined in the working calendar associated with the task plan. A day is defined (by default) as being 8 hours; therefore, a duration of 1 day in a task is 8 hours. |
Finish | The date on which a task is scheduled to finish. |
Name | The name of a task (or a task plan). |
Predecessors | The unique ID for a predecessor task in the task plan. |
Resource Names | The name of the resource (or resources) who are assigned to a task in a task plan. |
Start | The date on which a task is scheduled to start. |