Adding a schedule dependency
If a work item contains a task that is externally visible, Once a schedule dependency has been created, it is visible in the Cross-project Dependencies tab. Once you have made at least one task in a work item as externally visible, the item, with the milestones you selected as externally visible, will appear in the Cross-project Dependencies tab of the parent work item. You can also select that work item to show in the Cross-project Dependencies tab for other items. Once you have at least two items showing to the Cross-project Dependencies tab, you can then create a dependency between the two items. The tasks that you chose to be externally visible appear as the milestone diamonds on the Gantt bar.
- Open the Projects module.
- Select a work item.
- Select the Cross-project Dependencies tab.
- Click the milestone (diamond) in the Gantt bar to which you want to add a schedule dependency. When the cursor changes to a four-headed arrow, drag it to the milestone (diamond) that will be the schedule-dependent milestone.
- In the Dependency Creation dialog box, enter a name and description for this dependency.
- Click Save.
Deleting a schedule dependency
Once a schedule dependency has been created, it is visible in the Cross-project Dependencies tab. In order to change a dependency, you must first remove it, and then create a new dependency to replace it.
- Open the Projects module.
- Select a work item.
- Select the Cross-project Dependencies tab.
- Select the dependency arrow you want to delete and press the delete key on your computer.
Making tasks externally visible
In order to show work item milestones on the Cross-project Dependencies view, you must first make at least one task in the work item externally visible to other users in the Tasks tab.
- Open the Projects module.
- Select a work item.
- Select the Tasks tab.
- Click Check Out to check out the project plan.
- Select a task that you want to make externally visible.
- In the lower pane, on the Details tab, under Milestone Mapping select Task Externally Visible.
- Click Milestone Mapping. In the Map Milestone dialog box, select the milestone to which you want to map the task.
- Click OK.
- In the lower pane, click Save.
- Click Check In to check in the project plan.
Viewing a schedule dependency
Once a schedule dependency has been created, it is visible in the Cross-project Dependencies tab. In order to change a schedule dependency, you must delete it and then add a dependency to replace it.
- Open the Projects module.
- Select a work item.
- Select the Cross-project Dependencies tab.