Linking two tasks in the work breakdown structure view

A dependency (often called a linked task) determines how a task in a task plan is scheduled, in relation to all other tasks in the task plan. A dependency is based on a task's start date and/or finish date. A dependency that determines how other tasks in a task plan are scheduled is called a predecessor. A dependency that relies on another task's start date or finish date to determine how it can be scheduled is called a successor.

You can link two tasks together in the work breakdown structure view. Just select the task from which you want to create the dependency, and then drag it to the task to which you want to create the dependency.

To link tasks from the work breakdown structure view

  1. Open the Projects module.
  2. Select an item.
  3. Select the Task Plan tab.