Editing the lag for a predecessor task

A predecessor is a task that determines when another task (a successor) can be scheduled. Lag occurs when there is a delay between two tasks that share a dependency. Lag time is entered as a duration or as a percentage of the task's duration, where a positive entry is used for lag time, for example 5d is a lag of five days.

To edit the lag for a predecessor task

  1. Open the Projects module.
  2. Select an item.
  3. Select the Task Plan tab.
  4. one
  5. two
  6. tsk_to_edit_the_lag_for_a_predecessor_task_db