Inserting a task in a task plan

YOU CAN ALSO RIGHT-CLICK TO DO THIS OPTION.

To create new tasks, just type the task name into the name column and hit Enter. This will create a 1 day task that starts on the project start date. The duration will show up as 1d?. The ? signifies that the duration is estimated. You may type in a new value to change the duration (and thus make it no longer estimated), or modify the duration with the mouse. For example, if you want to create a task that will last one hour, enter 1h.

Adding tasks is as simple as typing in am empty row in the Gantt spreadsheet. Normally, you give each task a name and a duration (in working days). You then assign dependencies between tasks by dragging one bar to another. This is more flexible than entering specific dates. Date constraints should be used sparingly

To add a task to a task plan

  1. Open the Projects module.
  2. Select an item.
  3. Select the Task Plan tab.