Projects → Work Items → Labor Assignments
The Labor Assignments tab is used to help project managers track and manage work items. You can add additional columns to the Labor Assignments tab by clicking the Properties button. Start (Plan) and Finish (Plan) are derived from the values on the item. Start (Actual) and Finish (Actual) are based on timesheet entries. Work (Plan) is initially derived from the value on the work item, but it can be updated when assignment values roll up to the item. Cost (Plan) is based on Work (Plan) plus the allocation rate. Columns for Percent Work Complete and Remaining Work may show as n/a whenever the value of actual work is greater than the value of planned work.
You can allocate generic resources to work items.
You can allocate resources to work items.
You can assign resources to work items.
You can delete a resource assignment or allocation made to a work item. Select an item and then click Delete Assignment.