Release Manager - Release Automation → Integration → Integrating with ChangeMan ZMF → Configuring ZMF Communication on the Mainframe → Configuring ZMF Approvers
You must configure approvers in ZMF as needed to initiate the installation and baselining of change packages.
For example, if you configure just one approver, the following happens:
Once the approval is given by the approver, the change package will go into APR status and the installation will be initiated.
The related ZMF approval deployment task will go into the In Progress state and will wait for the ZMF change package to be installed and baselined.
After the ZMF change package goes into BAS status, the related ZMF approval deployment task will go into the Complete state.
If your approval tasks are initiated from Release Automation, see the Serena Release Manager Getting Started Guide for more information on ZMF approvals.
NOTE In ChangeMan ZMF, specify approvers on the Planned Approvals panel in option A.A.5. Approvers must have approval authority.