ChangeMan ZMF Plugin → Using the ChangeMan ZMF Plugin → Configuring Tasks for ChangeMan ZMF Change Packages → Approving ChangeMan ZMF Change Packages
Approve/Reject Package allows predefined approvers to review change package information, components, and test results and approve or reject the change package for installation to a promotion site.
Approval may be required in your ChangeMan ZMF implementation. If so, you'll need to set up an approve deployment task.
To configure an approve change package action in a deployment task:
In the UI, point to each field for additional information.
Some of the fields are described in the following table.
| Field | Description | Example Values | 
|---|---|---|
| Package Name |  
				   Click the link icon to select a change package. From here, you can: 
  | 
 
				<select a change package> | 
| Environment | Select each environment in which you want to execute the task. These are the environments configured in the deployment path. For example, Dev, Test, and Prod. | <select Test> | 
| Approver | For each selected environment, select from the approvers. These are the approvers set up in ChangeMan ZMF. | <select approver> | 
| Schedule Options |  
				   For each selected environment, select the schedule option and fill out the additional fields that open based on your selection. Options include the following: 
  | 
 
				
Copyright © 2012–2018 Serena Software, Inc., a Micro Focus company. All rights reserved.