Demoting Baselines

Purpose

Demote baselines in order to move them to a lower stage in the Global Stage Lifecycle, and optionally, have their item files deployed to the associated area(s).

Note that refactoring changes will not necessarily be deployed. It is recommended that you deploy refactoring changes using requests.

PRIVILEGES  
Demote a baseline to the next stage in the GSL (BASELINE_DEMOTE_NEXTSTAGE).

Demote a baseline to any stage in the GSL (BASELINE_DEMOTE_ANYSTAGE).

To deploy demoted baselines to a non-default area, you need the Deploy a baseline (BASELINE_DEPLOY) privilege for the area to which you want to deploy.

To demote baselines:

  1. Do one of the following:

  2. a    On the My Current Project tab or Baselines tab, select one or more baselines.

    b    Click the More button and select Demote.

    OR

    a    On the Deployment tab, select the History tab, and select one or more baseline promote events.

    b    Click the Demote button.

  3. On the first page of the Demote Wizard:

  4. Click Next.

  5. Optionally, on the Deploy to Areas page:

  6. Unless you have the necessary privilege, you will not be able to select any areas other than the default area(s) or deselect any default areas.

  7. Click Next.

  8. A Summary page is displayed informing you of the actions to be carried out.

  9. Click Finish.

Related Topics

Demote Wizard