Use this dialog box to create a revised release baseline from a release baseline.
Use the General tab to specify the baseline and its scope.
See Attributes Tab/Page for how to view and change the user-defined attributes of a baseline.
General Tab
| 
   Field  | 
  
   Description  | 
  
   Rules and Guidelines  | 
| 
   Baseline Specification  | 
  
   The ID of the selected baseline.  | 
  
   The new baseline inherits the product ID.  | 
| 
   New Baseline ID  | 
  
   Type a unique name or label for the baseline.  | 
  
   This name must be unique within the product. Maximum length is 128 characters.  | 
| 
   Type  | 
  
   Select a baseline type.  | 
  
   The default is the type of the selected baseline. Baseline types are defined in the Administration Console. For more information, see the Process Configuration Guide. If user-defined attributes exist for the selected type, use the Attributes tab to view and change these entries.  | 
| 
   Requirements  | 
  
   Select this option if you want to include/exclude item revisions based on related requirements.  | 
  
   
  | 
| 
   Requests  | 
  
   Select this option if you want to include/exclude item revisions based on related requests.  | 
  
   
  | 
| 
   Update Baseline using  | 
  
   The list of requests used to update item revisions in the baseline. Type, or copy, one or more request IDs, or click the Browse button to find them.  | 
  
   See Revising Baselines for details of how the requests are processed. Use commas to separate request IDs in the list. Request IDs have the following format: productID_changedocType_ number You can select a maximum of 496 requests.  | 
| 
   Remove From Baseline  | 
  
   The list of requests used to remove item revisions in the baseline. Type, or copy, one or more request or requirement IDs, or click the Browse button to find them.  | 
  
   See Revising Baselines for details of how the requests are processed. Use commas to separate IDs in the list. Request IDs have the following format: productID_changedocType_ number  | 
| 
   Traverse Request Relationships  | 
  
   Check to include item revisions in all requests related to the requests that are listed above.  | 
  
   
  | 
| 
   Project/Stream Selector  | 
  
   Check Use global or Use current  | 
  
   The project/stream determines which item revisions are available for inclusion in the baseline. If you check Use global, the top-level design part determines which item revisions are available for inclusion in the baseline.  | 
| 
   Product  | 
  
   Select the product whose items you want to include in the baseline.  | 
  
   The default is the product for the project/stream. The product does not have to match the product ID for the baseline you are creating.  | 
| 
   ID  | 
  
   Select the project or stream.  | 
  
   The default is the current project/stream.  | 
Related Topics
When Would I Create a Baseline?