Use this procedure to deploy one or more baselines to deployment areas associated with the project/stream. These baselines need to be at a stage that is the same or higher than the stage associated with the deployment areas.
Specify a schedule (a date and time in the future when the baseline(s) will be deployed).
If the deployed item(s) are part of a build configuration, start a build after the deployment has completed.
If you select more than one baseline, they must all be in the same product.
PRIVILEGES
To deploy baselines to a non-default area, you need the Deploy a baseline (BASELINE_DEPLOY) privilege for the area to which you want to deploy.
You cannot deploy baselines to an area that is associated with a stage in the GSL that is greater than the stage of those baselines.
To deploy a baseline:
On the Deployment tab, select the Pending tab or History tab, and select one or more request entries in the list.
Click the Deploy button.
Accept the default stage, or select another stage (if available) from the Deploy Stage list.
For Reason for deployment, optionally type a comment.
Optionally, on the Deploy to Areas page:
If you want the deployments to be queued immediately, select as soon as possible.
If you want the deployments to be scheduled for a particular time, select at specified time, and use the date picker to select a date and time.
Under Area(s) for deployment, select the area(s) to which you want to deploy.
Unless you have the necessary privilege, you will not be able to select any areas other than the default area(s) or deselect any default areas.
Click Next.
A Summary page is displayed informing you of the actions to be carried out.
Click Finish.
Related Topics