Step
|
Description
|
42
|
The release manager deploys the release packages to production.
|
43
|
The IT team implements requests for change.
|
44
|
The remaining deployment tasks continue to run automatically and the software is deployed to production.
|
45
|
The release manager transitions the release to its final state, Completed.
|
46
|
The release manager transitions the development package, requests, and tasks to their final states.
|
47
|
The development manager closes the ALM project.
|