Adding a status policy
When a policy is set, project managers will be required to approve status for task-based assignments. A status approval policy is independent of a time approval policy.
- From the application toolbar, click Setup, and then select Customization.
- Select the Timesheet Settings tab.
- Select the Approval Policy tab.
- To require approvals, under Status Approval, select Project Manager Approval Is Required.
- Click Save.
Adding an approval policy
When a policy is set, project and resource managers will be required to approve time for task-based assignments and resource managers will be required to approve time for activity-based assignments.
- From the application toolbar, click Setup, and then select Customization.
- Select the Timesheet Settings tab.
- Select the Approval Policy tab.
- To require approvals, under Time Approval, select Project Manager Approval Is Required, Project Manager Approval Is Required, or Project Manager Approval Is Required.
- Click Save.