Adding a time approval policy

When a policy is set, project and resource managers will be required to approve time for task-based assignments and resource managers will be required to approve time for activity-based assignments.

To add a time approval policy

  1. From the top-level navigation, open the Admin module.
  2. Select Customization.
  3. Select the Timesheet Settings tab.
  4. Select the Approval Policy tab.
  5. To require approvals, under Time Approval, select Project Manager approval is required for task-based assignments, Resource Manager approval is required for task-based assignments, or Resource Manager approval is required for activity-based assignments.
  6. Click Save Save.