Schedule variance. The difference in costs between current progress and expected progress. The calculation for schedule variance is as follows: SV = BCWP - BCWS. When the schedule variance is less than 0, it is an indicator that the task plan is behind schedule.
Copyright © 2003–2009 Serena Software, Inc. All rights reserved.