Reference → Glossary → E → EAC
Estimate at completion. The expected cost to complete all remaining work. The calculation for estimate at completion is as follows: EAC = ACWP + (BAC - BCWP). BAC - BCWP represents the planned costs of all uncompleted tasks. This is sometimes referred to as the estimate to complete (ETC).