Reference → Glossary → C → Critical Path
The critical path represents a task (or a series of tasks) that must be finished on time in order for the task plan to be finished on time. The critical path is based on the longest possible sequence of tasks, factoring in their start dates, finish dates, dependencies, and constraints. It compares the calculated finish date of the last task in the sequence to the planned finish date for the task plan.
Copyright © 2003–2009 Serena Software, Inc. All rights reserved.