Projects → Task Plan → Using Task Plan Tables → Schedule Variance
The Schedule Variance task plan table is used to compare baseline start and finish dates with current start and finish dates so that you can see how the task plan is doing in relation to where it should be.
Schedule Variance Fields | Description |
---|---|
Baseline Finish | The original, planned finish date for a task (or a task plan). |
Baseline Start | The original, planned start date for a task (or a task plan). |
Finish | The date on which a task is scheduled to finish. |
Finish Offset | The difference between the baseline finish date for a task and the current, actual, scheduled finish date. |
Name | The name of a task (or a task plan). |
Start | The date on which a task is scheduled to start. |
Start Offset | The difference between the baseline start date for a task and the current, actual, scheduled start date. |