Customization → Labor Attribute Mapping → Activity-based Items
The labor attribute maps for an activity-based item work differently than those for a task-based item; you can only use an allocation-based labor attribute map. Because there are no task assignments in activity-based items (only allocations), time logged against an activity-based item is logged directly against the item and not against an assignment. This means that while allocations roll up the same way as for task-based items, timesheet actuals, since there are no assignments, roll up (in the actual dimension) through the allocation map.
Activity-based labor attribute maps roll-up allocations made against items to the Plan dimension and roll-up user timesheet that has been submitted against an item. Before labor attribute mapping can be configured, be sure that a mappable Timephased - FTE attribute has been added.