Copy Dimension

The Copy Dimension dialog box helps you copy dimensioned attribute values from one dimension to the other. You can elect to copy all the data or copy only the data that falls within the specified date range. When data is copied data into a dimension, all data in that dimension is overwritten; if data is copied from within a specified date range, only the data in that date range is overwritten. Copying a dimension does not affect the task plan data. (You cannot copy data to the Plan or Actual dimensions.)

Copying a dimension

Use the Copy Dimension dialog box to copy data from one dimension to another.

To copy a dimension
  1. Open the Projects module.
  2. Right-click an item from the item tree, and then click Copy Dimension.
  3. In the Copy Dimension dialog box, select the dimension from where you are copying data and the dimension to where the data will be copied.
  4. Select the dimension from which you want to copy data in the Copy from list and the dimension to which you want to copy data in the Copy to list. You cannot copy data to a locked dimension.
  5. You can copy all data or you can copy data for a specific date range. Under Timeframe, specify the starting and ending dates.
  6. Click Save.